01
Part Is Free in One Year, Onlie Service Is Provide
Part Is Free in One Year, Onlie Service Is Provide
1m3/Min;
10 Sets/Month
Industrial Filtered Water
Pressure0.4-0.6MPa
soar
Wooden Box
6750*550*1350mm
China
Product Description

ngth of 4~6m, and pressure ≤4Mpa.
The hydraulic press adopts the middle pipe inlet and outlet type, the clamp is set at the central
pressure test station of the hydraulic press, and the pipe inlet/outlet is automatically lifted and
moved.
The steel pipe with a spray port welded on the pipe requires the buyer to manually assist the s-
ingle pipe inlet.
Steel pipe O.D. 25~48.3mm,0.8mm alarmed automatically if have leakage hole;
Steel pipe O.D. 60.3~88.9mm,2.0mm alarmed automatically if have leakage hole.

Equipment | Power/kW | Qty/set | Total kW |
Hydraulic pump 28ml/r | 15 | 1 | 15 |
Water injection pump 32m,12m3/h | 5.5 | 1 | 5.5 |
High pressure booster pump 4Mpa,3m3/h | 4 | 1 | 4 |
Stepper tube shifter motor | 4 | 1 | 4 |
Lifting and panning steel inlet/outlet pipe unit motors | 4 | 2 | 8 |
Water injection/exhaust seal seat drive motor | 5.5 | 2 | 5.5 |
Total | 47.5 |




1 Environment: temperature 5~50°C (can be used in winter as long as it is not frozen), humidity 10%~100%, sei-
smic intensity 8 degrees;
2 Power supply: voltage AC 380V±10%, frequency 50HZ±1, power 50kW;
3 Water supply: industrial filtered water (tap water can be used), total floating matter ≤5mg/L, hardness ≤10.6Dh,
pressure 0.15~0.50MPa;
Circulating water, pressure 0.15~0.50MPa;
4 Compressed air: pressure 0.4~0.6 MPa, flow rate: 1m3/min;
5 Test liquid: water + emulsifier, ratio 3% ~ 5%, liquid circulation;
6 Hydraulic oil: 46# anti-wear hydraulic oil.
1.1.4 Steel pipe parameters
1 Outer diameter of steel pipe (mm): ¢33.4mm~88.9mm;
2 Length of steel pipe (mm): 4~6m, the length deviation of each batch of steel pipes is less than 5mm
3 Wall thickness of steel pipe (mm): mm
4 End form of pipe: with groove or thread
Process flow
Material storage rack → the step-by-step pipe moving device moves four steel pipes to the material waiting rack →
the horizontal feeding conveying device rises and horizontally moves the steel pipe to be pressure tested to the pr-
essure testing station of the hydraulic press → clamps → the pressure test heads at both ends move forward → pip-
e end seals → water injection and exhaust → exhaust valve closes → water injection valve closes → pressurization
→ pressure maintenance → pressure relief → pressure test heads at both ends move back → release the clamps →
steel pipes are sent out → next cycle.